OliverMcMillan
reportedly has all the permits it needs from the city of Atlanta to begin
construction at the Buckhead Atlanta and BuckheadView was told Wednesday that
the latest report is that real work will begin on the site in August.
In response to a
question Wednesday, city planner Karl Smith-Davids told BuckheadView that that
all of the permits necessary to start construction at the Buckhead Atlanta have
been issued by the city and had been issued for some time.
| City planner Karl Smith-Davids is shown at a recent meeting of the SPI-9 Development Review Committee along with other committee members, left to right, Sally Silver, Denise Starling and Bonnie Dean. |
Smith-Davids, who is the
city’s planner assigned to both Special Public Interest districts 9 and 12 in
Buckhead (SPI-9 and SPI-12) said he is not sure why OliverMcMillan had not yet
begun work on the project, but it was not for lack of the city issuing the
necessary permits.
Smith-Davids, who spoke
to BuckheadView at the end of the SPI-12 Development Review Committee meeting,
said he understood that the developer was working out some minor changes on the
site plans, but that does not affect the permits that have been issued or the
start-up of work on the project.
Smith-Davids is the
person in the city’s Planning Department who is most directly involved with the
approval of the development plans, zoning issues and permits for the Buckhead
Atlanta development.
Denise Starling,
executive director of Livable Atlanta and BATMA as well as a member of both the
SPI-9 and SPI-12 Development Review Committees, told BuckheadView she had been
told in a conversation with OliverMcMillan Development Director Hunter Richardson
that work would begin at the site in August.
![]() |
| OliverMcMillan's Buckhead Atlanta Director of Development Hunter Richardson is shown with the new model of the proposed development. |
Both of those
conversations on Wednesday afternoon confirm Richardson’s response last week to
questions from BuckheadView regarding what was holding up construction work.
Richardson at that time denied that rumors of problems with the financing for
the development was holding up the start of construction.
Richardson
told BuckheadViewtoday that pre-construction activities are underway and
OliverMcMillan is working “diligently to get Buckhead Atlanta back under
construction.” He added that the project continues “to be on schedule for a
late 2013/early 2014 opening."
"OliverMcMillan
continues to work diligently to get Buckhead Atlanta back under construction,”
Richardson’s emailed statement said last week. “Pre-construction activities are
underway with the former Hi-Fi Buys building having been refurbished for its
current use as Balfour Beatty's construction offices and Georgia Power in the
process of under grounding the power lines on Buckhead Avenue. This effort is
just weeks away from completion. Since much of this work is underground, it is
not yet visible to the public. This work is part of the process of preparing to
start construction.”
Asked why OliverMcMillan had not been back to the SPI-9 DRC since February with answers to some requested plan changes, Richardson’s statement said: “We continue to work with the DRC and the city of Atlanta to obtain the necessary approvals and permits to restart the development. We already have SAP (Special Administrative Permit) and SDP (Site Development Plan) approvals for Parcels A and C and are in the process of obtaining the framing permits to commence construction. We continue to be on schedule for a late 2013/early 2014 opening."
Asked why OliverMcMillan had not been back to the SPI-9 DRC since February with answers to some requested plan changes, Richardson’s statement said: “We continue to work with the DRC and the city of Atlanta to obtain the necessary approvals and permits to restart the development. We already have SAP (Special Administrative Permit) and SDP (Site Development Plan) approvals for Parcels A and C and are in the process of obtaining the framing permits to commence construction. We continue to be on schedule for a late 2013/early 2014 opening."
| Hunter Richardson at a Neighborhood Planning Unit B meeting last September is shown describing the different parcels of the Buckhead Atlanta development. |
Richardson
reported he has not been back to the DRC because, currently, he has the
approvals needed to go to construction, and is focused on getting construction
re-started.
On
Wednesday afternoon, Smith-Davids said he expects OliverMcMillan to returns to
the DRC sometime in the next few months.
Richardson
had sent a response to a query from Starling as to whether OliverMcMillan would
be at Wednesday’s SPI-9 DRC meeting, which stated: "We had not been
planning on coming back to DRC in July as the next round of reviews by DRC are
not needed for our next round of permits which are the framing permits. While
we continue to work on open issues with City Planning on the Parcel B SAP, we
have not yet nailed down the design/budget re the streetscape/landscape items
proposed for Parcels A and C. Once finalized, we plan to return to DRC.”
Richardson explained in his memo to Starling: “Parcel B won't start construction until months after we start Parcels A & C and the streetscape work is a year out before it starts."

John:
ReplyDeleteThanks for keeping us all posted on this very important subject. Let's hope the 'plans' happen when they say.
Tom H.